Quick Summary
Whole house rewiring usually takes about two weeks of work for a typical home, but the timeline depends on home size, age, and what electricians find once walls are open. Older homes with knob-and-tube wiring often take longer. Treat any schedule as an estimate until an electrician assesses the specific house.
Planning a whole house rewire in Idaho?Electric Falls assesses older homes and builds a realistic rewire schedule for Southeast Idaho.Request Your Rewire Assessment
Most homeowners asking how long whole house rewiring takes want a number they can plan around. The honest answer: the timeline depends on home size, age, and what electricians find once walls are open.
A whole house rewire means replacing the electrical wiring throughout the home, including circuits, outlets, switches, and often the panel. It is a series of stages that must happen in order, each depending on the one before it.
Timelines vary for a few reasons:
Treat any schedule as an estimate rather than a guarantee.
The timeline for a 2,000-square-foot house depends on how many rooms need open walls, attic and crawl space access, and whether the panel is replaced at the same time. An electrician can give a schedule after an assessment of the specific home.
A common mistake is judging the timeline by how long the wire takes to pull. Pulling cable is often the quick part. Opening and closing walls, patching plaster, and waiting on inspections can add more days than the wiring itself.
Three things drive most of the variation: home size, age, and existing wiring type.
Home size is the easiest to estimate. Each additional room adds outlets, switches, and cable runs. A small home might need only a few days; a large home can stretch into several weeks.
Home age matters more than most people expect.
Wiring type can change the job dramatically. Modern cable is relatively easy to replace. Older systems need more care to confirm what is live, what is abandoned, and what is safe to remove.
Knob-and-tube wiring was common in homes built before the 1930s, and it is still found in older Idaho houses. This type of wiring uses separate porcelain knobs and tubes with uninsulated conductors, and it was not designed for today's electrical loads.
Replacing knob-and-tube usually adds time because the old wire is often buried in insulation, sealed behind walls, or connected to newer work in ways that are hard to trace. Electricians typically need to open more walls and confirm every circuit before disconnecting anything. A licensed electrician can assess the existing system before any work begins.
Each of these can add days. Good planning reduces the chance that one derails the whole project.
The article breaks down how each factor shifts the schedule, so the table below puts the main drivers side by side.
Here is a sample schedule for a typical occupied single-family home of roughly 2,000 square feet with a panel replacement.

Day 8: Rough-in inspection. The rough-in must be inspected before walls are closed.
Days 9-10: Panel and service work. The panel is upgraded or replaced and connected to the service.
Days 11-13: Finish work (second fix). Outlets, switches, and light fixtures are installed. Walls are patched where they were opened.
Day 14: Testing and final inspection. Every circuit is tested for continuity, grounding, and GFCI and AFCI function.
In some cases, yes. Electricians can sometimes run new cable through attics, crawl spaces, and existing wall cavities without opening large sections of drywall or plaster.
Still, most full rewires require opening at least some walls. Outlets and switches have to be reached, and older wiring often runs through places that cannot be accessed from above or below.
A common approach is to open only the walls that must be accessed and leave the rest intact. This keeps repair costs down and shortens the finish work.
Many homeowners stay in the house during a rewire, but whether that works depends less on the size of the job than on how the crew sequences power and access.
A full rewire is usually done circuit by circuit rather than by shutting off the whole house for the duration, so power availability changes daily. A typical pattern looks like this:
A room-by-room view helps you plan daily life:
Occupied versus vacant timelines differ in concrete ways:
Before work starts, agree on a power plan with the electrician: which rooms will be affected on which days, where temporary power will come from, and how you will be notified of whole-house outages.
Preparation makes a real difference in how smoothly the project goes.
If you are planning a whole house rewire in Southeast Idaho, start by getting an assessment from a licensed electrician who can review your home's age, size, and existing wiring.
Electric Falls serves homeowners in Idaho Falls, Rexburg, Rigby, and Ammon, with residential rewiring, panel upgrades, and whole-home surge protection. When you are ready to plan your project, request service from Electric Falls to set up an assessment. You can also learn about our residential electrical work.
If your home has older wiring or a panel that needs attention, contact Electric Falls about urgent safety concerns before a full rewire begins. Taking that step early can make the larger project safer and easier to schedule.
The timeline for a 2,000-square-foot rewire depends on the number of circuits, how accessible the wiring is, and whether the home is occupied. Simpler layouts can finish sooner, while homes with plaster walls, multiple stories or hidden wiring runs take longer. Ask your electrician for a schedule that separates workdays from calendar days, since inspections and material delivery add time that does not show up in the labor hours.
Yes, in many cases a rewire can be done with limited wall openings by running cable through attics, crawl spaces, basements and existing chases, then making small access holes at outlets, switches and fixtures. Homes with plaster and lath, or with wiring that must be routed through solid walls, usually need more openings and patch work. The right approach depends on the home's construction, so a site assessment before work begins gives the most accurate answer.
Many homeowners stay in the house, but the power will be off or interrupted at times, and rooms may be opened up in stages. Moving out is most useful when the work involves a full panel replacement, extensive wall opening or long outages. Plan for temporary power arrangements for refrigeration, medical equipment or home offices, and ask the electrician which rooms will be disrupted on which days.
Clear access to walls, attics, crawl spaces and the electrical panel, and move furniture and valuables away from areas being opened. Confirm with your electrician which circuits will be off and when, arrange for a temporary power plan, and make sure pets and children are kept away from work areas. Keep a list of appliances and electronics you want protected, and ask about a surge protection device as part of the upgrade.